Is there Value in the Noika Test
A few years ago Bas Vodde defined a simple test to help his coaching group determine whether teams were trying to be agile and whether it would be worth investing coaching time with these teams.
As described by Joe Little, the test is:
The Nokia Test is in two parts.
First, are you doing Iterative Development?
- Iterations must be timeboxed to less than 4 weeks
- Software features must be tested and working at the end of each iteration
- The Iteration must start before specification is complete
The experience is that if you ask a lot of “Scrum” teams if they can pass this part of the test, they can’t. If you are at a conference, often not a single team in the room.
The next part of the test checks whether you are doing Scrum (in Nokia’s opinion):
- You know who the product owner is
- There is a product backlog prioritized by business value
- The product backlog has estimates created by the team
- The team generates burndown charts and knows their velocity
- There are no project managers (or anyone else) disrupting the work of the team